An Inquiry on the Waste Transport System for the Side Wall Expanding Project in Waitoushan Iron Open Pit
歪头山铁矿扩帮开采工程岩石运输系统方案的探讨
作者: QU AiqiaoHAN YanqingMI ChangSchool of Resource and Civil Engineering,Laoning Institute of Science and TechnologyWaitoushan Iron Open Pit Benxi Syeel Group Co.Ltd
刊名: Journal of Liaoning Institute of Science and Technology, 2015(02), pp.22-24
中文刊名: 辽宁科技学院学报, 2015(02), pp.22-24
来源数据库: CJFDTEMP_U
DOI: CNKI:SUN:BXGZ.0.2015-02-010
关键词: Waitoushan Iron Open PitSide wall expanding projectRock waste transportationTransition from wall expanding
中文关键词: 歪头山铁矿扩帮开采岩石运输扩帮过渡
英文摘要: Along with the side wall expanding project carry out forward deep lying seam,current transport system will be destroyed.The paper introduces the scheme selection based on current transport system.According to the technical- economic comparison with three schemes,we determine the truck road and rail scheme used for waste transport system.
中文摘要: 根据歪头山铁矿深部扩帮开采工程,矿山上盘现有的运输系统将受到破坏,本文针对矿山新的岩石运输系统的选择,在考虑现有运输系统利用的基础上,对三种不同的岩石运输方案分别做了基建投资和技术经济分析比较,最终确定了歪头山铁矿扩帮开采工程岩石运输方案,为扩大矿山生产规模和扩帮过渡提供依据;矿山采用本文推荐的汽车—铁路(倒装)岩石运输系统方案,可以减少基建投资和岩石运输成本,实现矿山平稳扩帮过渡,达到矿山扩帮增产开采的目的 。
全文获取路径:  
分享到:

×
关键词翻译
关键词翻译